Our vision is to build a community center so we can serve those in need more effectively. The community center will house an Orphanage, Vocational Training Center, Community Kitchen, Warehouse, Medical Clinic, Place of Worship, Gymnasium, and Playground. Since we received the land at our current location, we have been building according to our vision, slowly but surely, with the help of many volunteers and donations across the US.

If you are interested in helping us finish our community center, please visit Volunteer page and Goods and Material page for details.

We will periodically update the section below to let you know the progress of construction.

Construction Update

January 2013

Community Kitchen and Dining Hall

In the last 12 months, we:

1. Finished tiling dining area.
2. Reinforced structure of dining hall.
3. Replaced wood doors with metal security doors.
4. Textured and painted dining hall.
5. Installed baseboards on wall.

We still need to:

1. Put in sheetrock, tape, texture, paint, tile, and install baseboards in kitchen and pantry.
2. Install kitchen cabinets.
3. Finish plumbing and connect sinks.
4. Finish building stalls and putting in sinks in bathroom.

Orphanage

In the last 12 months, we:

1. Almost completed insulation and sheetrock.
2. Taped all the rooms.
3. Put in commercial tiles on all but one room and one bathroom.
4. Did electrical work.

We still need to:

1. Install five windows, one security door, and light fixtures.
2. Finish plumbing, electrical work, and tiling.
3. Build stalls and install toilets and sinks in the bathroom.

Training Center

In the last 12 months, we:

1. Reorganized and set up computers for computer training class.
2. Repainted the room.

We still need to:

1. Acquire newer computers compatible for internet use.

Sanctuary

In the last 12 months, we:

1. Raised and put in new roof to prevent further water damage in Sanctuary.

We still need to:

1. Work on interior walls and ceiling to accomodate newly raised roof.
2. Rewire electricity circuit.

Medical Clinic

In the last 12 months, we:

1. Covered the wall connected to the sanctuary.

We still need to:

1. Put in electricity and plumbing.
2. Frame interior walls and bathroom.
3. Work on insulation, sheetrock, texturing, and painting.
4. Install window, sinks and toilet.
5. Tile the floor.
6. Furnish clinic with medical equipment and supplies.

Office

We still need to:

1. Lay concrete slab and put on a roof in order to start working on the interior.

Grounds Keeper's Residence

In the last 12 months, we:

1. Painted walls and put in baseboards.
2. Provided new furniture for grounds keepers.
3. Finished tiling the bathroom and shower.

We still need to:

1. Install ceiling fans and kitchen cabinets.

Grounds

In the last 12 months, we:

1. Started building railings that lead to second floor and sliding metal gate to the property.
2. Completed footings for the sidewalk.

We still need to:

1. Lay concrete slab for parking lot.
2. Expand the driveway to accomodate construction vehicles.

Working on the roof.

Tiling the floor in dining hall.